HS2 first part complete value may very well be ‘many billions’ above estimate – report

The Government has insisted works on its main excessive pace rail line undertaking are “inside funds”, regardless of a declare that the primary part may run to “many billions” greater than estimated.

A report offered to the HS2 board by the undertaking’s deputy chair Sir Jon Thompson stated it was “most unlikely” that the £40.3 billion goal value for the London to Birmingham part could be met, the Financial Times reported.

Section One has a goal value of £40.3 billion, however the Authorities has beforehand stated the “funding envelope” for it’s £44.6 billion, which features a contingency of £4.3 billion.

The leaked doc, dated June this yr and seen by the newspaper, can also be reported to have concluded there was solely a 50% probability the additional contingency funds could be sufficient to cowl the fee.

Sir Jon was appointed as a non-executive director of HS2 Ltd in April 2021, and have become deputy chair in March this yr.

His evaluation is reported to state that the primary part’s complete value was prone to be “many billions greater than the reported estimate”.

The Monetary Instances stated Sir Jon’s report additionally warned that rising inflation is presenting a “important and rising problem” and that persevering with to file prices in 2019 costs means not one of the figures mirrored “what has been or is being paid”.

The Authorities stays dedicated to delivering it on time and to funds

Authorities spokesman

It added: “In nearly each space reviewed important developments are deliberate in 2022/23 which affect on the estimates and danger.”

However the Authorities has stated it’s dedicated to delivering the undertaking on time and inside its funds.

A spokesman stated: “HS2 is below means, inside funds, and supporting 28,000 jobs. The Authorities stays dedicated to delivering it on time and to funds.

“As with all initiatives of this scale, contracts and scope are routinely thought-about to make sure they proceed to ship the worth for cash for taxpayers.”

The Authorities sparked anger in November 2021 when it revealed its Built-in Rail Plan (IRP), which included scrapping HS2’s jap leg between the East Midlands and Leeds.